Pro Builders Express, Inc
Page 1 of 7
Office (562)921-5000
Fax (562)921-5055
Date: 15-Sep-20
DEMOLITION
The Manor I a beautul designed 400 sqft 2nd story ADU built over the top of a
detached garage with a exterior stairway consisting of 1 bedroom , 1 bathroom
, kitchen , living room and laundry .
-
Demolition Of Non-Reinforced Concrete Slab Up To 4" Thick And Dumping Of
Debris. 100 sqft.
-
Supply Labor For Demolition Of Stucco And Lath From Exterior Walls And
Dumping Of Debris Sqft. 100 sqft.
-
Removal of eave overhang at existing roof structure as required for new
addition. 80 Lf.
-
Supply labor and material to remove existing garage door and header for new
second story ADU. 8 mh.
DEMOLITION 2
-
Supply Labor For Demolition Of Composition For Maximum Of 2 Layers Of
Composition Roofing From Roof Per Square And Disposal Of Debris Square.
Excludes sheathing replacement. 7 square.
- Demolition Of 2" X 8" Wood Roof Rafters As Required. 600 sqft.
FOUNDATION/FOOTINGS
-
Supply Labor And Equipment For A Concrete Pump To Remote Location For
Pumping Of Concrete As Required. 1 Pump.
-
Concrete Cutting Of Reinforced 4" Slab Concrete per lineal ft. 120 lf.
-
Pour A 31/2" 2500 Psi Reinforced Concrete Slab On Grade With Typical
Excavation, 2" Slab Base, Wire Mesh, Forms And 10 mil visqueen Vapor
Barrier. "Contractor Cannot Be Responsible For Minor Cracks In Concrete
During The Curing Process." Standard installation for new room addition
foundation. 100 sqft.
SECOND STORY FOUNDATION
-
Excavate And Finish A 24" X 12" Reinforced Concrete Footing With Reinforcing
Steel Tied And Finished At Grade. Include Hold downs, anchor bolts and 2500
PSI concrete. 60 ft.
FRAMING
-
Supply labor and material to frame a 4 x 4 doug fir post for new
construction as required. 12 ea.
-
Framing Installation Of Pressure Treated 2" X 4" X10' Sill Plate Including
Drilled And Installed With Foundation Bolts. Sill Plate Including Drilled
And Installed With Foundation Bolts. 120 ft.
-
Frame Interior And Exterior Walls With 2"X 4" Douglas Fir 16" On Center
Interior And Exterior Walls As Required.
- Supply labor and material to frame a window opening at new construction with
proper size header and kraft paper as specified. 5 openings.
-
Supply labor and material to cut and hang 2"x6" doug fir ceiling or floor
joist at 24" on center at new addition. 400 sqft.
-
Supply labor and material to cut and hang 2"x10" doug fir ceiling or floor
joist at 20" on center at new addition. 400 sqft.
-
Supply Labor And Material For Cut And Stack Framing Of 2"X 6"X 16'str & Btr
Studs With Roof Rafters Of 16" On Center For New Roof Area. 700 sqft.
-
Frame Up To 3' Door Opening In Wood Stud Wall With Appropriate Header. 4 ea.
-
Installation Of 8" X 10" Douglas Fir Flush Beam As Required For Bearing Wall
Up To 12'span For A Single Story. 0 ft.
-
Installation Of 8" X 10" Douglas Fir Flush Beam As Required For Bearing Wall
Up To 12'span For A Single Story. 0 ft.
-
Supply Labor And Material To Frame Up To 8' bi-Pass Closet Door Opening In
Wood Stud Wall With Appropriate Header. 1 ea.
-
Installation Of 5 1/4" X 12" glue laminated Flush Beam As Required For
Bearing Wall Up To 18'span For A Single Story. 20 lf.
-
Supply Labor And Material To Rough Frame a 3 foot Douglas Fir Stairway 11
1/2" Thread And 71/2" Risers With 5/8" Plywood Threads And Box Construction
Design Per Tred for interior stairway. circular or custom stairway
additional.
-
Supply Labor And Material To Install 2" X 6" Rough Sawn Facia Along Edge Of
Roof Line For New Addition. 80 ft.
-
Supply labor and material to install 5/8" cdx plywood sheathing over new
addition include radiant barrier and simpson strapping as specified. (Code
Plus +) GREEN BUILDING 700 sqft.
-
Supply Labor And Material To Install 1" X 6" X 12'sel-J Grade Spf Pine Ship
Lap Roof Sheeting At Perimeter Eve Of New Addition. 80 lf.
-
Supply Labor And Material To Install 3/4" Sturdy Floor Tongue And Groove
Floor Sheeting As Required For Underlayment At Second Story Of New Addition.
400 sqft.
-
Supply Labor And Material To Install 4' X 10' X 1/2" Struct 1 Plywood Or
Diagonal Struts As Required At New Addition For Earthquake Shear Panel.
(CODE PLUS)+ 1600 sqft.
SECOND STORY FRAMING
-
Installation Of 8" X 10" Douglas Fir Flush Beam As Required For Bearing Wall
Up To 12'span For A Single Story. 16 lf.
ROUGH PLUMBING
-
Supply labor and material to install a 1/2" vertical and 4/3" horizontal Pex
or copper hot and cold supply and 3" abs drain waste with cleanouts 10 ft
tie in within foundation perimeter. 4 fixtures.
-
Supply Labor And Material To Install Solvent Welded 4" Abs Soil Pipe From
Perimeter Of House To Main Sewer Line From Street, Included Major Trenching
As Required. Excludes sewer locating if required. 40 ft.
-
Supply Labor And Material To Install 3/4" X 10' Sch 40 Black Pipe For Gas
Line To Remote Fixture Location In Wall. Includes gas test excludes under
concrete installation and meter relocation. 80 ft.
- Supply Labor And Material To Install A A.O. Smith Signature Premier
50-Gallon Tall 12-year Limited 40000-BTU Natural Gas Water Heater and
Pressure Relief Valve. Includes Earthquakes Strapping And Supply Flex. 1 ea.
ROUGH ELECTRICAL
-
Supply Labor And Material To Install Standard Grade 15a 125v 2 Pole 3 Wire
Grounded White Or Ivory Duplex Receptacle At New Addition. 12 ea.
-
Install Standard Grade White Or Ivory 15a/120v Quiet One Way 20 Amp Switches
And Switch Covers As Specified. 5 ea.
-
Install Standard Grade White Or Ivory 15a/120v Quiet Three Way Switch And
Switch Cover As Specified. 1 ea.
-
Supply Labor And Material To Install Install Single Gang Box's, Square Or
Round Boxes For Outlet, Switch Or Light Receptacles With 14/2 Type Nmb Romex
Grounded Wiring At New Addition. 24 ea.
-
Installation Of A Levitron Decorator Gfi 15a/125v Ivory Or White Gfi
Receptacle Outlet. 8 ea.
-
Supply Labor And Material To Install A Leviton Exterior Gfi 20a/125v White
Electrical Outlet With A Plastic One Gang Decorator Waterproof Cover. 1 ea.
-
Supply Labor And Material To Install One 100 Amp Flush Mount Electrical
Service Panel With Circuit Breakers And Mast. Maximum Run 15 Ft. Panel To Be
Spotted By Southern California Edison. Includes Small Junction Box. 1 panel.
-
Supply labor and material to install a Pass & Seymour/Legrand White Wall
Occupancy Sensor at new addition. 5 ea.
-
Supply labor and material to add additional 120 volt circuit as required for
new lighting and power as required at new construction. 12 circuit.
-
Installation Of dedicated Arc fault circuit breaker as required for bedrooms
15a/125v Ivory Or White Gfi Receptacle Outlet. 12 AFCI.
-
Supply Labor And Material To Install 110 Volt Ac/Dc Hard Wired With Battery
Backup Smoke Detectors As Required For New Bedrooms For Fire Code
Requirements. 2 ea.
-
Install a Carbon Monoxide Detector 85 decibel alarm Battery operated
Permanent sensor Test/reset button Updates every 15 seconds With Digital
Reading From 0-999 Ppm And Powerful 85 Decibel Alarm. Required 1 ea.
ROOFING
-
Supply Labor And Material To Install GAF or equal Class A Fire Rating 30
Year Dimensional Composition Shingle Over Roof Area As Specified. Includes
2" Drip Edge Seal And Paint All Vents. 5 Year Warranty On Labor. (CODE
PLUS)+ 7 squares
INSULATION
-
Supply Labor And Material To Install R-13 or R-15 as required Roxul wood
unfaced batt insulation 15" X 3 1/2" Batt Insulation At Exterior Walls Of
New Addition. Includes Expanding Foam And Caulking As Required t-24 green
building. 640 sqft.
-
Supply Labor And Material To Install R-19 or R-23 as required Roxul wood
unfaced batt insulation 23" X 6 3/4" Batt Or Roll Insulation At Raised
Floors Of New Addition t-24 green building. 400 sqft.
-
Supply Labor And Material To Install R-30 or R-38 as required Roxul wood
unfaced batt insulationrt Therm 16" X 10 1/4" Batt Or Roll Insulation At
Ceilings Of New Addition t-24 green building. 400 sqft.
Pro Builders Express, Inc
Page 4 of 7
Office (562)921-5000
Fax (562)921-5055
Date: 15-Sep-20
HEATING
-
Supply Labor And Material To Install A Williams or equal 25,000 Btu Single
Wall Recessed Or Surface Mount Gas Heater Matchless Pilot Igniter Including
Ventingb With A Built-In Thermostat At New addition. 1 ea.
DRYWALL
-
Supply Labor And Material To Hang And Tape 1/2" Dry Wall On All Specified
Walls And Ceilings Of New Addition Includes Orange Peel Or Knockdown
Texture. Smooth Wall Texture Additional. 1680 sqft.
-
Supply Labor And Material To Hang And Tape 5/8" Dry Wall On All Specified
Walls And Ceilings Of New Addition Includes Orange Peel Or Knockdown
Texture. Smooth Wall Texture Additional. 1040 sqft.
FINISH CARPENTRY
-
Supply labor and material to install a prehung Therma-Tru Benchmark Doors
Right or Left Hand Inswing Fiberglass Entry Door with Insulating Core at new
addition. Excludes lockset. 1 ea.
-
Supply Labor And Material To Install A JELD-WEN prehung Colonist Primed
6-Panel Hollow Core Molded Composite Single Prehung Door right or
left-handed excludes lockset. 3 ea.
-
Supply Labor And Material To Install A Kwikset Satin Nickel Bed/Bath Door
Knob lockset at the new door. Model 92001-095. 3 ea.
-
Supply Labor And Material To Install A Kwikset Satin Nickel Residential
Entry Door Lever with Deadbolt entry lock At New Door. 1 ea.
-
Supply Labor And Material For Installation Of Single Piece 3/8" X 2 1/4"
Streamline Primed Base Molding Along Baseboard Area. 120 ft.
-
Supply Labor And Material For Installation Of 9/16"x 1 9/16" Primed MDF
bevel Door Case Moulding At New Addition. 96 ft.
-
Installation Of Closet Shelf And Pole With 2" X 12" #2 pine closet shelf and
pole 1 3/8" D.F. closet rod at the closet interior. Pine And 1 3/8" D.F.
Closet Rod. 12 ft.
WINDOWS
-
Supply labor and material to install Pella Thermastar series nail on vinyl
low E, dual glaze argon gas insulated, clear, or obscure glass nail-on
windows at new construction per building code, allowance of $250.00 per
window. Standard T-24 green building. Limited lifetime warranty. 5 windows.
EXTERIOR FINISH
-
Supply Labor And Material To Apply 3 Coat Stucco, Scratch, Brown And
Colorcoat To Exterior Walls And Ceilings In Textured Or Sand Finish At New
construction contractor Cannot Be Responsible For Minor Cracks In Stucco
During The Curing Process or variations in stucco color from existing or
color chip excludes foam trims or painting. 1000 sqft.
-
Supply Labor And Material To Install Paper Back Metal Lath Stapled Onto
Frame To Prepare For Scratch Coat at new construction. 1000 sqft.
BATHROOM FIXTURES
-
Supply Labor And Material To Install A Style Selections Morriston White
Single Sink Vanity with White Engineered Stone Top Bathroom Vanity At New
Bathroom Addition. 1 ea.
- Supply Labor And Material For Installation of Pfister Masey Brushed Nickel
2-handle Widespread Bathroom Faucet at new addition. 1 ea.
-
Supply Labor And Material To Install A Pfister Masey 1-Handle Tub and Shower
Faucet in Brushed Nickel includes shower head standard installation. 1 ea.
-
Supply labor and material to install KOHLER Verticyl White Undermount
Rectangular Bathroom Sink with Overflow sink at bathroom. 1 sink.
-
Supply Labor And Material To Install a KOHLER Highline Classic White
Water Sense Labeled Elongated Chair Height 2-piece White Bathroom Toilet At
New Bathroom Addition. 1 ea.
-
Supply Labor And Material To Install A Delta Laurel High Gloss White Shower
Wall Surround Side and Back Wall Kit at new bathroom Delta Laurel High Gloss
White Acrylic Shower Base. 1 ea.
-
Supply Labor And Material To Install A 31 In. To 32-1/2 In. Opening Swinging
Shower Door, Sterling Plumbing Silver Frame Obscure Glass Pivot Shower Door.
Standard. 1 ea.
-
Supply Labor And Material To Install a Pfister Selia Brushed Nickel Single
24" Towel Bar at bathroom. 1 ea.
-
Supply Labor And Material To Install A Utilitech Ventilation Fan 2-Sone
70-CFM White Bathroom Fan ENERGY STAR With 3" Duct To Exterior Includes
Switch a. For Baths Up To 65 Sqft. 1 ea.
-
Supply Labor and material to install NGY or similar pre-fabricated medium
grade 3/4" Quartz countertop cut to size with square edges over rough top
with a 6" splash allowance of $200 per 9 ft section standard installation.
12 sf.
-
Supply Labor And Material To Install Ceramic Tile Over Wonder Board,
Includes Standard Ceramic Tile @ $4.00 Sqft Laid In Straight Pattern.
Diagonal Patterns Or Liners Additional $1.50 Per Sqft. Includes floors
located in Bathroom Standard installation. 50 sqft.
FINISH ELECTRICAL
-
Supply Labor And Material To Install A Project Source 2-Pack 7.4-in W White
LED Flush Mount Light ENERGY STAR Light Fixture At New Addition. 2 ea.
-
Supply Material And Labor To Install a Good Earth Lighting Jordan 11-in W
Satin nickel LED Flush Mount Light ENERGY STAR at new addition. 1 ea.
-
Supply Labor And Material To Install Portfolio 3-Light 23.5-in Weathered
Bronze Vanity Light at bathroom addition excludes glass shades. 1 ea.
-
Supply Material And Labor To Install A Secure Home 9.52-in H Matte Black
Motion Activated Outdoor Wall Light At New Addition. 2 ea.
KITCHEN FIXTURES
-
Supply labor and material to install one 1/2" supply line and 1/4" supply
for refrigerator ice maker with supply valve and filter. 1 supply line.
-
Supply labor and material to fabricate and install custom poplar kitchen
cabinets with 3/4" solid birch interiors including drawers, Euro hinges and
full extension rails, interiors to be sealed twice, exterior to be stained
to owner's choice and sealed with gloss lacquer finish. Excludes optional
door pulls, knobs. Allowance of $4,800 for cabinets and installation. 14 lf.
KITCHEN FIXTURES
Supply Labor And Material To Install A Elkay Double-Basin Stainless Steel
Undermount Kitchen Sink Kitchen Sink With Flex Supply Lines And Drain As
Specified. Standard installation nickel design series 1 ea.
-
Supply Material And Labor To Install A Home-Vue 1'1/2' X 4' 4 Light
Flourescent Light With White Steel Frame And White Drop Acrylic Diffuser On
Ceiling. 1 ea.
-
Supply Labor and material to install owner supplied appliances for new
kitchen to include standard Dishwasher, Oven, Stove as required 4
appliances. Custom appliances installation additional cost 1 4 appliance.
-
Supply Labor And Material To Install A Nutone 30" White Whispair decorator
210 Cfm Range Hood Kitchen Exhaust Fan As Specified With 6 Inch Vent Ducting
Through Wall Or Roof. Standard installation 1 ea.
-
Supply Labor And Material To Install A In Sink Erator 1/3 Hp Badger1 Garbage
Disposal At Kitchen Area 1 Year Warranty. 1 ea.
-
Supply Labor and material to install NGY or similar pre-fabricated medium
grade 3/4" Quartz countertop cut to size with square edges over rough top
with a 6" splash allowance of $200 per 9 ft section standard installation.
36 sf.
EXTERIOR STAIRWAY
-
Supply Labor And Material For Fabrication And Forming For A 12" X 12" Pad
Footing With Reinforcing Steel As Required. 2 pads.
-
Frame Up Douglas Fir Steps 3 Or More High, 36" Wide With 12" Thread And 12"
Risers And 2" X 6" Douglas Fir Open Riser Design Per Riser. 36 riser.
-
Installation Of 42" High Deck Redwood Railings 2" X 4" Ballisters With
Bottom Rail And 2" X 6" Top Rail Per Lin Ft. 25 ft.
PERMITS/PLANS/MISC.
-
This estimate good for 45 days from original date, contracts after this date
are required to be approved by Pro Builders Express Inc. 1.
-
Removal And Dumping Of Approximately 40 Cubic Yards Of Construction Debris
Per Load Excludes recycling fees if required by city 50% recycled, Green
Building. 14 loads.
-
Customer to relocate existing sprinkler system as required for construction
of room addition. 1.
-
Homeowner to choose all material, fixture, and color choices before project
walkthrough and start of project. 1 choice.
-
These items are specifically excluded from this estimate, others may also be
excluded: 1 Total.
Pro Builders Express, Inc
Page 7 of 7
(866)360-1526
Office (562)921-5000
Fax (562)921-5055
Date: 15-Sep-20
This is a quotation based on Customer Specifications and by itself is not a
contract to do Work. Pro-Builders Express cannot be responsible for changes in
Work or Price due to County, State or Federal Building Requirements that were
not Specified nor Based on Approved Plans. Items noted as standard are subject
to additional charge if changed to a custom installation by owner.